To reduce electrical procurement costs, put the whole BOQ into one RFQ, allow approved equivalents where the specification permits, avoid over-specified ratings, and order in drum lengths and standard pack quantities. Place long-lead items early, ask for documents with the quote, compare landed cost rather than unit price, and standardise brands across the site.
Step by step
- Consolidate the BOQPut every electrical line of the package into one RFQ with the BOQ item numbers, so the supplier prices the whole list and can combine deliveries.
- Check what the specification allowsMark the lines where a maker is fixed and the lines where "or approved equivalent" is allowed, and remove ratings that go beyond what the design needs.
- Round to drum lengths and pack quantitiesConvert cable runs into standard drum lengths and small items into the maker’s pack quantities, with a sensible allowance for waste.
- Release long-lead items firstOrder switchgear, Ex equipment and special cables as soon as the submittal is approved, before the common items.
- Ask for documents with the quotationRequest datasheets, test certificates and origin details at the RFQ stage so the submittal is not rejected later.
- Compare landed cost and standardiseCompare offers on delivered cost, documents and lead time, then keep the same brands and a short spares list across the site.
Cost drivers and what to do about them
The price on the quotation is only part of what a package costs. Re-orders, rejected submittals, waste and site delays often cost more than the difference between two offers.
| Cost driver | What to do |
|---|---|
| Many small orders to many suppliers | Consolidate the BOQ into one RFQ per package and keep the BOQ item numbers |
| One maker fixed for every line | Ask whether "or approved equivalent" is allowed, and where it is, request alternatives marked clearly |
| Ratings higher than the design needs | Check breaking capacity, IP rating, cable size and material against the design, not against habit |
| Odd cable lengths and part packs | Order standard drum lengths and pack quantities; plan cuts from the drum schedule |
| Long-lead items ordered late | Release switchgear, Ex equipment and special cables first, as soon as approval allows |
| Rejected submittals | Ask for datasheets, test certificates and origin details with the quotation |
| Cheapest unit price, extra costs later | Compare landed cost: delivery, documents, lead time and validity included |
| Mixed brands on one site | Standardise brands and keep a short spares list of common items |
One RFQ instead of many small orders
Splitting a package into many small enquiries means each supplier prices a short list, delivery is charged many times, and your team spends hours chasing quotes. A single RFQ for the package lets the supplier price the whole list together and plan combined deliveries.
Keep one line per item with the description, maker and part number (if known), quantity, unit and key ratings. Keep your BOQ item numbers, so the offer can be checked line by line against the tender. Excel, a PDF BOQ or a drawing schedule all work.
Equivalents and over-specification
Where the project specification allows "or approved equivalent", say so in the RFQ. An equivalent must match the ratings, standard, dimensions and certificates the specification asks for, and on consultant-supervised projects it is used only after the submittal is approved. Our cross-reference tool helps you find candidate equivalents before you send the list.
Over-specification is a quiet cost. Common examples:
- A breaking capacity far above the fault level calculated for the panel.
- Stainless steel or a high IP rating on items installed indoors in a dry room.
- A cable size picked up from an older job rather than sized for the actual load, run length and installation.
- Ex-certified items listed for areas that are not classified as hazardous.
Do not reduce a rating on your own: raise it with the designer or consultant, and change it only through the project’s approval route.
Drum lengths, pack quantities and long-lead items
Cable is made and stocked on drums of standard lengths, and small items such as lugs, glands, ties and fixings come in maker’s packs. Cutting cable to odd lengths or breaking packs adds handling cost and waste. Build a drum schedule from the cable runs, group runs of the same cable onto standard drums, and round small items up to full packs.
Some items take much longer to arrive than common stock, mainly switchgear assemblies and ACBs, Ex equipment for hazardous areas, and special cables (large sizes, fire-resistant, instrumentation or non-standard constructions). Lead time depends on the maker and the item, so ask for it per line in the quotation. Release these items as soon as the submittal is approved, so the programme does not force you into expensive last-minute substitutes.
Documents first, then landed cost
A rejected material submittal costs time and often a second purchase. Ask at the RFQ stage for what the specification needs: datasheets, test certificates or type test reports, certificate of origin, and conformity documents where the product falls under a Saudi technical regulation. Check the country of origin against any approved list in the contract before you order.
When you compare offers, compare landed cost, not unit price. Look at delivery to site, the documents included, the lead time per line, the validity of the offer and whether the offered item is exactly what was asked or an alternative. An offer that is lower per unit but late or missing documents is rarely the cheaper one.
Standardise brands and keep a spares list
Using the same breaker, contactor, gland and lug ranges across a site reduces the number of different spares, keeps accessories interchangeable and makes maintenance simpler. Agree the preferred ranges with the client and consultant at the start of the job.
Keep a short spares list of common items: MCBs and MCCBs in the ratings used, contactor coils, fuses, glands, lugs, cable ties and lamps. Re-ordering from a known list with fixed part numbers is quicker and avoids mistakes. To price your package, e-mail sales@sixwinds.com.sa or use the quotation form with your BOQ, the maker rule, the documents you need and the delivery location.
Common questions
What is the quickest way to lower the cost of an electrical package?
Send the whole BOQ as one RFQ, allow approved equivalents where the specification permits, and order in standard drum lengths and pack quantities.
Does "or approved equivalent" mean any cheaper brand can be used?
No. The equivalent must meet the same ratings, standard, dimensions and certificates, and the consultant or client must approve the submittal before it is used.
Why compare landed cost instead of unit price?
Delivery, missing documents, long lead times and re-orders all add cost. The landed cost shows what the item really costs on site.
Which items should be ordered first?
Long-lead items such as switchgear, ACBs, Ex equipment and special cables. Ask for the lead time per line and release them as soon as the submittal is approved.
How does standardising brands save money?
It reduces the number of different spares, keeps accessories interchangeable and makes re-ordering simpler and less error-prone.
Need these items? E-mail your list or a nameplate photo to sales@sixwinds.com.sa, or use the RFQ form.
This guide is general information. Final selection must follow the project design, the applicable standards and the maker's data.
